TL;DR
Wallonia ordered Google to suspend construction on a three-hectare building at its planned Farciennes data centre, saying it lacked proper planning permission. Google says work is paused while it awaits guidance and has challenged the region’s refusal of a proposed change to water cooling; a court hearing is scheduled for January.
Walloon regional authorities have ordered Google to stop construction on a building at its planned data centre in Farciennes, southern Belgium, saying the three-hectare structure was built without proper planning permission. Google says it has paused work while awaiting further guidance, as a related dispute over permission to use water from the River Sambre for cooling is due before a court in January.
A regional official told AFP that inspectors visited the site on Thursday and instructed Google representatives to halt construction. Nicolas Yernaux, a spokesman for Wallonia’s regional authorities, described the work as “a major offense” involving the construction of a building covering three hectares. The stated basis for the order is a lack of proper planning permission. The order itself was not available online in the source reporting, so its full wording and scope could not be independently reviewed.
The dispute concerns a building on a former mining site of about 50 hectares, not, according to the report, the entire site. Google had originally planned to use air cooling, Belgian media reports cited by AFP said. The company later applied to change the project to use water drawn from the nearby River Sambre. Regional authorities rejected that application over the summer, with concerns about water use heightened by severe droughts since spring, AFP reported.
Google has challenged the refusal in court, with a hearing scheduled for January, AFP reported. The company told the BBC that work in Farciennes had been paused “pending additional guidance” and said it remains “committed to complying with local laws.” Greenpeace Belgium said this week that drone footage showed work continuing, and alleged that the latest version of the planning permission had been revoked in August. Those claims have not been established by a court ruling in the available reports.
Stop-work order · court hearing pending
How a cooling plan became a stop-work order
At the heart of the row is water: how the computers are cooled, and where the water comes from.
- The planAir coolingThe original project planned to cool the computers with air, Belgian media reported.
- The changeRiver waterGoogle applied to cool the site with water from the nearby River Sambre.
- SummerRequest refusedAfter a dry spring, regional officials refused the change. Google went to court.
- This weekStop-work orderInspectors told Google to halt building. Officials call it a major offence.
- NextCourt in JanuaryGoogle says it paused the works and will follow local laws.
- Blue: the former mining site, some 50 hectares.
- Orange: the building of three hectares that officials say lacks proper permission.
Sources: AFP, as published by Arab News, November 27, 2026; BBC News, November 29, 2026. Schematic.
Graphic: Powered by Thorsten Meyer AI
Water Permits and AI Infrastructure
The order puts a local planning dispute directly in the path of a large technology project, illustrating how construction permits and water access can affect data-centre development alongside land and power. Data centres house computers used for websites, apps and AI services, and require systems to remove the heat generated by that equipment. A change in cooling design can bring a project into a new permitting process and prompt scrutiny of the resources it would use.
For nearby residents, the immediate issue is whether construction complies with local approvals and how the proposed cooling system could affect a river during dry conditions. For Google and its suppliers, a stop-work order can delay part of a project while the legal and planning questions are resolved. Cloud and AI customers may also care if permitting delays affect when new computing capacity becomes available, though the reports provide no estimate of any delay or its effect on services.
The source reporting says the building at issue covers three hectares, roughly four football pitches, while the wider former mining site covers about 50 hectares. The order’s reported focus on one building matters: it does not establish that all work across the wider site has been halted.
Products Worth Considering

Anker SOLIX C1000 Gen 2 Portable Power Station

Kindle Paperwhite Signature Edition, 32 GB (12th Generation, 2024), Metallic Black

Logitech MX Mechanical Wireless Illuminated Keyboard, Tactile Quiet, Graphite
As an affiliate, we earn on qualifying purchases.
How the Farciennes Dispute Developed
The conflict developed in stages. Google sought approval to change the project’s cooling approach from air to water drawn from the River Sambre. Regional authorities refused the requested change over the summer. The site was then inspected, and authorities ordered construction to stop after identifying what they described as an improperly permitted building.
Greenpeace Belgium’s account adds a separate allegation: the group said drone footage showed construction continuing and said the latest planning permission had been revoked in August. Greenpeace’s statement is a campaign group’s claim, not a judicial finding. Google’s stated position is that work has been paused pending guidance and that it intends to comply with local law. The legal challenge to the refusal of the cooling-permit change remains pending.
The Farciennes case is not the only reported dispute involving Google data-centre construction. AFP reported that Finnish authorities halted work at two Google data-centre sites in October. That separate action does not determine the Belgian case, but it places the Farciennes order amid wider scrutiny of data-centre projects and their local approvals.
“We have operated in Belgium for over 15 years and remain committed to complying with local laws.”
— Google, in a statement reported by the BBC
Questions the Order Leaves Open
The full stop-work order has not been published in the reporting provided, leaving its precise legal wording and any conditions unclear. It is also not clear whether authorities could later approve or legalise the building, or what steps Google would need to take before construction can resume.
The reports do not state how much water the proposed cooling system would use, how any withdrawal would be managed, or whether the company has proposed an alternative. The court has not yet ruled on Google’s challenge to the regional refusal. Greenpeace’s claim that work continued and its account of the permit’s revocation also remain allegations in the available material.
It is not clear whether construction elsewhere on the 50-hectare site is affected. The reported order concerns the three-hectare building; the available reports do not establish a site-wide shutdown or quantify the project’s cost, schedule impact, or implications for Google’s services.
Court Hearing and Permit Decisions
The next identified legal milestone is the January court hearing on Google’s challenge to the refusal of its requested cooling-permit change. The hearing may clarify the status of that application, but the available reporting does not say whether it will also decide the separate planning-permission issue cited in the stop-work order.
Until further guidance or a legal decision changes the situation, Google says work in Farciennes is paused. Regional authorities’ next steps, any revised application from Google, and whether construction can resume remain unreported. The order’s implementation and the outcome of the court process will determine how the project proceeds.
Key Questions
Why did Wallonia order Google to stop construction?
Regional authorities said a three-hectare building was being constructed without proper planning permission. A regional spokesman called it a “major offense.”
What is the dispute about the River Sambre?
Google sought to change its cooling plan from air cooling to using water from the River Sambre. Regional authorities refused the application over the summer, amid concerns about water use and drought conditions, according to AFP.
Has Google stopped all work at the site?
Google told the BBC that work in Farciennes had been paused pending additional guidance. The reported order concerns one building; the available reports do not confirm that all activity across the wider site has stopped.
When will the legal dispute be heard?
A court hearing on Google’s challenge to the refusal of its cooling-permit change is scheduled for January, AFP reported. The reporting does not specify whether that hearing will resolve the separate planning-permission issue.
Source: ThorstenMeyerAI.com